防水工程施工方案 |
添加时间:2018/4/10 14:30:05 浏览次数: |
1、编制依据
1. Compiling the basis
根据北京市××建筑设计研究院设计的北京××工程的地下室防水工程设计图纸、《北京市地下室防水推荐做法》及本工程施工组织设计。
According to the design drawings of the basement waterproof engineering of the Beijing x * * project in Beijing, the design of the waterproof recommendation method of the basement of the Beijing and the construction organization of the project.
2、工程概况
2. Engineering survey
地下室底板平面面积约××m2,分为六块,间有伸缩缝5条,伸缩缝宽度7cm。地下室负二层,底板到±0.000为6m,立面面积约为××m2。
The floor area of the basement floor is about X m2, which is divided into six parts, including 5 expansion joints and 7cm expansion joints. The basement has two layers, the bottom plate to + 0 is 6m, and the facade area is about m2.
3、施工进度
3. Construction progress
×月×日开始施工,到×月×日底板施工完毕,立面施工到保护墙等同高度、其余立面随土建混凝土墙面进度进行。
The construction starts on October, October, and the construction of the bottom plate is completed until the month of October, the height of the protection wall is equal to the height of the protection wall, and the other facades go along with the progress of the civil concrete wall.
4、施工准备
4. Construction preparation
4.1施工面的水混找平层应压平抹光,坚实平整,含水率≤90%,以保证材料粘贴牢固。
4.1 of the water leveling layer should be flat light, solid flat, moisture content is less than 90%, to ensure the material solid paste.
4.2底板平面涂一遍冷底油,干燥4小时。
4.2, the bottom plate is coated with cold bottom oil for 4 hours.
5、劳动组织
5. Labor Organization
×月×日×名持证上岗工人进入现场清扫施工面,涂冷底油。×月×日持证上岗人员可达到××人。
The workers who go to work on the spot will be cleaned at the scene and painted with cold base oil. XXX persons can be reached by XXX.
6、材料准备
6. Material preparation
材料选用SBS—25复合胎合格品,应带有出厂合格证、防伪标识和随料出厂质检单。材料×月×日进现场,不得交叉叠放。材料进场后由甲方、乙方和监理三方共同抽样,甲方复测,保证材料符合要求。
Materials used for SBS - 25 composite tire qualifying products shall be accompanied by factory certificate, anti fake identification and quality inspection sheet. The material XXXX into the site shall not be intersecting and stacked. After entering the field, the materials will be sampled jointly by Party A, Party B and the three party. Party A will repeat the test to ensure that the material meets the requirements.
7、施工方法
7. Construction method
底板平面由西向东采用热熔粘贴法铺贴两层卷材,第二层卷材的搭接缝应与第一层的错开25-30cm。卷材之间长边与短边的搭接均为10cm。阴阳角的附加层为3.3cm。
The bottom plane is paved with two layers of rolls from the west to the east by the hot melt bonding method. The lap joints of the second layers should be staggered 25-30cm with the first floor. The overlap between the long and the short sides of the material is 10cm. The additional layer of the Yin and Yang is 3.3cm.
立面永久性保护墙采用空铺法,主体下沉时可以避免拉断主体与保护墙连接处的材料。立面空铺到永久性保护墙相同高度时,甩出20—25cm、预留茬,预留茬应搭在保护墙的平面,茬头抹2—3cm泥巴保护层,以免损坏。主体超出永久性保护墙后,接茬搭接±0cm热熔翻贴在主体墙上。
The vertical permanent protective wall is made by empty paving. When the main body sinks, it can avoid breaking the connection material between the main body and the protective wall. When the elevation is spread to the same height of the permanent protective wall, 20 - 25cm and stubble are thrown out. The stubble should be put on the surface of the protective wall, and the stubble head should be covered with 2 - 3cm mud protection layer, so as to avoid damage. The subject is outside the permanent protection wall, Jiecha lap + 0cm turn on the body wall with hot melt.
底板伸缩缝采用“V”型空铺。
The floor expansion joint uses the "V" type empty shop.
立墙之间的伸缩缝采用延伸率200%以上的非下垂型密封膏填充2 cm,外部采用延伸率150%的卷材做成正V字型。
The expansion joint between the vertical walls is made up of a non droop type sealing paste with a elongation of more than 200%, which is filled with 2 cm. The outer roll of the rolled material with a elongation of 150% is made into a positive V font. |